( )is a method used in Critical Path Methodology for construcing a project achedule network diagram that uses hoxes or rectangles, referred to as nodes, to represe activities and connects them with arrows that show the logical relationships that exist between them.
A.PERT
B.AOA
C.WBS
D.PDM
参考答案:D