Which of the following steps is least likely to be an administrative step in the capital budgeting process()
A. Arranging financing for capital projects.
B. Conducting a post-audit to identify errors in the forecasting process.
C. Prioritizing projects according to project profitability and company resources.
参考答案:A
解析:
Arranging financing is not one of the administrative steps in the capital budgeting process. The four administrative steps in the capital budgeting process are: Idea generation Analyzing project proposals Creating the firm-wide capital budget Monitoring decisions and conducting a post-audit