问题
单项选择题 案例分析题
In project management, a()(1) is a listing of aproject's milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimatedin terms of resource ()(2) ,budget and duration, linked by dependencies and scheduled events.
空白(1)处应选择()
A.schedule
B.activity
C.plan
D.contractor
答案
参考答案:A