You have to finish a project with in 2 weeks and your lead developer had to take 1 week leave due to personal emergency.Another project manager has agreed to loan the service of his lead developer for 1 week.You are taking his help and completing the project.This case is an example of () (Choose the best answer).
A.fast tracking
B.crashing
C.risk management
D.resource leveling
答案
参考答案:B
解析:
你在两周内就要结束项目,你的首席开发者因为个人事务离开一周。另一个项目经理同意让他的首席开发者过来帮助,你接受了这个帮助完成了项目。这是的例子(选择最佳答案)。 A) 快速跟进 B) 赶工 C) 风险管理 D) 资源平衡 你的开发者离开了,其他的开发者过来帮助,等于加速了项目进展。有些人会选择C,如果选项C写风险应对,可能更好些。