You are the project manager for software development project.The feasibility study can start any time and takes 1 week and requirement gathering takes 2 weeks which can start only after feasibility study.The design and test plan development can start in parallel after the requirements gathering.Test plan preparation takes 8 weeks followed by a review by the customer and the time estimated for review is 1 week.After the review,Test data preparation takes 6 weeks.Design takes 6 weeks and it is followed by development and unit testing,for one module it takes 2 weeks and for the other module it takes 2 weeks.There are no dependencies between modules and they can be developed simultaneously.After test data preparation and development and unit testing of both the modules,there is 2 weeks system testing.What is duration of the critical path ?()
A.14 week
B.15 week
C.20 week
D.19 week
参考答案:C
解析:
你是软件开发项目的项目经理。可行性研究可在任何时间开始,需要花费1周;需求收集必须在可行性研究完成之后进行,需要花费2周。设汁和测试计划开发可以在需求收集后并列进行。测试计划准备需要花费8周,接下来是客户评估,客户评估预计花费1周。评估之后,测试数据准备需要花费6周。设计花费6周,接着是开发和单元测试,其中一个模块花费2周,另一个模块花费2周。模块之间没有依赖关系,可以同时开发。测试数据准备和开发和单元测试之后,有2周的系统测试。项目关键路径的历时是多少 A) 14周。 B) 15周。 C) 20周。 D) 19周。 关键路径为:可行性研究 测试计划开发 客户评估一设计一开发和单元测试系统测试。历时为:1+8+1+6+2+2=20周。