A change request in a project has been rejected some weeks ago.Yesterday,the project manager found out that it nevertheless has been implemented by the team members,who knew of the change request,but not of the rejection.In order to avoid such a situation,rejected change requests are input to which process ?()
A.Schedule developmen
B.Scope verificatio
C.Monitor and control project wor
D.Information distributio
参考答案:C
解析:
一个变更请求在几周前被拒绝。昨天,项目经理发现这个变更还是被团队成员实施了,因为他们知道这个变更请求但不知道被拒绝了。为避免这种现象,拒绝的变更将输入到哪个过程 A) 制定进度表。 B) 核实范围。 C) 监视与控制项目工作。 D) 信息发布。 在2004版中,拒绝的变更需要继续监控;在2008版中,拒绝的变更要退回请求方,以便补充信息。