In order to speed up a project,you made a decision to fast-track a phase currently performed with five team members and another one which was planned to begin in four weeks time with another five team members.Which of the following activities should you do first ?()
A.Make sure that all exit criteria of the consecutive phase have been met to ensure the flow of communications in a team situation which is more complex by a factor of 2.
B.Make sure that all entry criteria of the previous phase have been met by planning and performing a phase gate meeting to assess technical aptnes
C.Make sure that all exit criteria of the previous phase have been met by planning and performing a phase gate meeting to assess technical performanc
D.Restructure your team and delegate tasks in order to ensure the flow of conmunications in a team situation which is more complex by a factor of 4.5.
参考答案:D
解析:
为了加速项目,你决定快速跟进某个阶段,这个阶段现在由5个团队成员执行;另一个将在第四周开始,由其他5个团队成员执行。你应该首先进行下列哪项活动 A) 确认所有后续阶段的退出标准被满足.确保沟通顺畅,因为这种情况下沟通比以往复杂了2倍。 B) 通过计划和执行一个阶段会议来评估技术能力,以确认所有之前的阶段的进入标准被满足。 C) 通过计划和执行一个阶段会议来评估技术绩效,以确认所有之前的阶段退出标准已经被满足。 D) 重组你的团队并分配任务以确保沟通顺畅,因为这种情况下沟通比以往复杂了4.5倍。 快速跟进表明两个阶段同时进行,代表同时有10个团队成员共同工作,原来渠道为10个,现在为45个,45除10为4.5,所以说现在沟通比以前复杂了4.5倍。