You are working as a project manager for a major US-based public company.This morning you received alarming news that the major strategic project you are responsible for will not be able to provide financial benefits to the organization as expected.This drawback will significantly influence future profits of the entire corporation.What should you do right now ?()

A.You should not overact and check at least three options before making any decision

B.You must immediately inform the corporate management to ensure real time issuers disclosure

C.You should investigate detailed information on the problem before escalating it to corporate managemen

D.You should find a quick solution for the problem and implement this immediatel

答案

参考答案:B

解析:

你是一个总部设在美国的上市公司的项目经理。今天上午,你收到令人震惊的消息,由你负责的一个重大战略项目将无法从组织中获得预期的财政支持。这将大大影响今后整个公司的利润。你现在应该怎么做 A) 不要发火,在作出任何决定之前至少制订三个可选方案。 B) 必须立即通知公司管理层,确保问题及时被讨论。 C) 在问题升级到公司管理层之前,调查该问题的详细信息。 D) 迅速找出解决问题的办法,而且即刻履行。 及时与干系人沟通。