If task A has seven days of free float and 15 days of total float and the early start date is delayed 5 days, what does this do to the completion date of the project
A) Pushes the finish date out ten days.
B) Delays the early start date of the next dependent task five days.
C) Allows the project to finish five days earlier.
D) The finish date doesn't change.