In the process of communication requirement analysis, the project manager should consider the number of potential communication channels or paths as an indicator of the complexity of a project’s communication. According to Metcalfe’s Law, a project with 10 stakeholders has () potential communication channels.

A、10

B、45

C、50

D、100

答案

参考答案:B

解析:10*9/2=45,参考答案::B