All the following are purposes of project risk management EXCEPT______.
A.identifying factors that are likely to affect the project scopquality,time and cost
B.developing response strategies for all identified risks
C.providing a baseline for project factors that cannot be controlled
D.mitigating impacts by influencing project factors that can be controlled