Are you a man or a mouse When people ask this question they want to know (1) you think you are a (2) person or a coward. But you will never really know the answer to this question (3) you are tested in real life. Some people (4) they are brave but when they come face to face with real (5) , they act like cowards. Others think of themselves as cowards, but when they meet danger, they act like (6) .Lenny had always thought of himself as a (7) person. He got worried before examinations. He worried about his job and health. All he wanted in life was to be safe and healthy. (8) , on January 15th, 2002, a plane crashed into the Potomac River in Washington. Lenny went to the river to See what was happening. He saw a woman in the (9) water. Lenny did not feel afraid. He kept very (10) and did a very dangerous thing. He jumped into the Potomac, (11) to the woman, and kept her head (12) the water. Seventy-eight people died that day. Thanks to Lenny, it was not (13) .When you are in a very (14) situation and feel afraid, the body automatically produces a chemical in the blood. The chemical is called adrenalin. (15) adrenalin in the blood system, you actually feel per and per and are (16) to fight or run away. However, when you are absolutely terrified, the body can produce too much adrenalin. Where this (17) , the muscles become very hard and you find you (18) move at all. You are then paralyzed with fear. This is (19) when we are very frightened, we sometimes say we’re "petrified". This word comes from the Greek word "petros", which means "stone". We are (20) frightened that we become stonelike.

第(18)空应选择()

A.needn’t

B.can’t

C.mustn’t

D.shouldn’t

答案

参考答案:B

阅读理解与欣赏
问答题

某大型工业项目的主厂房工程,发包人通过公开招标选定了承包人,并依据招标文件和投标文件,与承包人签订了施工合同。合同中部分内容如下:

1.合同工期160天,承包人编制的初始网络进度计划,如图6-1所示。

由于施工工艺要求,该计划中C、E、I三项工作施工需使用同一台运输机械;B、D、H三项工作施工需使用同一台吊装机械。上述工作由于施工机械的限制只能按顺序施工,不能同时平行进行。

2.承包人在投标报价中填报的部分相关内容如下:

(1)完成A、B、C、D、E、F、G、H、I九项工作的人工工日消耗量分别为:100、400、400、300、200、60、60、90、1000个工日;

(2)工人的日工资单价为50元/工日;运输机械台班单价为2400元/台班;吊装机械台班单价为1200元/台班;

(3)分项工程项目和措施项目均采用以直接费为计算基础的工料单价法,其中的间接费费率为18%,利润率为7%,税金按相关规定计算。施工企业所在地为县城。

3.合同中规定:人员窝工费补偿25元/工日;运输机械折旧费1000元/台班;吊装机械折旧费500元/台班。

在施工过程中,由于设计变更使工作E增加了工程量,作业时间延长了20天,增加用工100个工日,增加材料费2.5万元,增加机械台班20个,相应的措施费增加1.2万元。同时,E、H、I的工人分别属于不同工种,H、I工作分别推迟20天。

对承包人的初始网络进度计划进行调整,以满足施工工艺和施工机械对施工作业顺序的制约要求。