问题
多项选择题
利用“香蕉”曲线可以( )。
A.合理安排进度计划
B.比较实际进度与计划进度
C.预测后续工程进度
D.推算工程总时差
E.分析进度偏差原因
答案
参考答案:A,B,C
利用“香蕉”曲线可以( )。
A.合理安排进度计划
B.比较实际进度与计划进度
C.预测后续工程进度
D.推算工程总时差
E.分析进度偏差原因
参考答案:A,B,C
阅读短文,判断句子正(T)误(F)。 | |
Chinese team. The football match is going to be over at six o'clock in the afternoon. Our teachers, Mr Li and Mr Wang, are going to watch the football match with us. We are going there by bus. We think we can come back at about eight in the evening. ( ) 1. There is a football match between a Chinese team and a Japanese team. ( ) 2. The match will be over at four o'clock in the afternoon. ( ) 3. We are going there by train. ( ) 4. Mr Li and Mrs Li are going to watch the match with us. ( ) 5. We will come back at about seven in the evening. |