问题 单项选择题

On some projects,especially ones of smaller scope,activity sequencing, activity resource estimating, activity duration estimating, and (70) are so linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

A.time estimating

B.cost estimating

C.project planning

D.schedule development

答案

参考答案:D