The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to ().
A.measure, delay, record, distribute, analyze, and direct
B.plan, schedule, monitor, control, report, and forecast
C.promote, highlight, monitor, control, forecast, and report
D.emphasize, visualize, analyze, conceptualize, report, and record
参考答案:B
解析:
[参考译文] 项目进度计划是规定在一段时间内相关活动的多文档,它代表该项目的时间维度,是一种用于决策的管理工具。因此项目管理团队可用它进行准备(plan)、议程(schedule)、监测(monitor)、控制(control)、报告(report)和预测(forecast)。