问题 阅读理解

阅读理解

     John is a fat (肥胖的) boy. He likes eating very much. For breakfast, he has eggs, milk oranges and

bananas. For lunch, he likes hamburgers and salad. And for dinner, he eats chicken,  tomatoes, French

fries and apples. For dessert, he has ice cream. But he doesn’t  play sports.

1. John likes ____ very much.

A. running

B. eating

C. playing sports

D. playing basketball

2. For breakfast, he has ____.

A. eggs, milk and apples          

B. milk, oranges and chicken

C. eggs, milk, oranges and bananas  

D. oranges, bananas , eggs and salad

3.He likes hamburgers and salad for ____.

A. breakfast  

B. lunch  

C. dinner  

D. dessert

4. He eats ____ for dinner.

A. chicken  

B. French fries  

C. tomatoes and apples    

D. A, B and C

5.Which one is right (正确的)?

A. John has tomatoes for lunch.    

B. John has ice cream for dinner.

C. John likes playing sports.        

D. John likes eating very much.

答案

1-5 BCBDD

单项选择题 A3/A4型题
问答题 案例分析题

某投资公司建造一幢办公楼,采用公开招标方式选择施工单位。招标文件要求:提交投标文件和投标保证金的截止时间为2011年5月30日。该投资公司于2011年3月6日发出招标公告,共有5家建筑施工单位参加了投标。第五家施工单位于2011年6月2日提交了投标保证金。开标会于2011年6月3日由该省建委主持。经过综合评选,最终确定第2家施工单位中标。投资公司(甲方)与中标单位(乙方)双方按规定签订了施工承包合同,合同约定开工日期为2011年8月16日。工程开工后发生了如下几项事件。

事件1:因拆迁工作拖延,甲方于2011年8月18日才向乙方提供施工场地,导致乙方A、B两项工作延误了2d,并分别造成人工窝工6个和8个工日;但乙方C项工作未受影响。

事件2:乙方与机械设备租赁商约定,D项工作施工用的某机械应于2011年8月28日进场,但因出租方原因推迟到当月29日才进场,造成D工作延误1d和人工窝工7个工日。

事件3:因甲方设计变更,乙方在E项工作施工时,导致人工增加14个工日,相关费用增加了1.5万元,并使施工时间增加了2d。

事件4:在F项工作施工时,因甲方供材出现质量缺陷,乙方施工增加用工6个工日,其他费用1000元,并使H项工作时间延长1d,人工窝工24个工日。

上述事件中,A、D、H三项工作均为关键工作,没有机动时间,其余工作均有足够的机动时间。

上述招标投标过程中,有哪些不妥之处?请说明理由。