问题 单项选择题

A project manager believes that modifying the scope of the project may provide added value service for the customer. The project manager should A.assign change tasks to project members B.call a meeting of the configuration control board C.change the scope baseline D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline ().

A.assign change tasks to project members

B.call a meeting of the configuration control board

C.change the scope baseline

D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

答案

参考答案:D

解析:

(非教材内容)

某项目经理相信: 修改项目的范围定义,可能为客户提供增值服务。该项目经理应该: 按照最初定义的项目基准完成项目。只有为增值服务项目筹措到资金后,再对项目范围定义进行修改。

单项选择题
单项选择题