Your project is in the planning phase and you are paid every fortnight for the work to be done during the fortnight. You have been informed by the project sponsor that there has been a revaluation of projects within your company and your project will not be getting any additional funding. In this case, you should ______.
A.stop work immediately and release all resources
B.perform appropriate closure for the project
C.decrease team size
D.remove non-critical tasks to decrease cost
参考答案:B
解析: 你的项目在计划阶段, 你已经支付这两周T作的费用。你被项目发起人告知: 你公司内部对项目进行了重新评估, 你的项目将不再获得另外的资金。在这种情况下, 你应该______。 A) 立刻停止工作并遣散所有资源 B) 为项目执行合适的收尾 C) 减小团队 D) 去掉非关键任务来压缩成本 一个项目或项目阶段在达成其目标或者由于其他原因终止时,都需要收尾。项目收尾需要记录项目成果被项目发起人或者客户正式接受,在特殊原因情况下收尾时,需要记录项目成果完成情况和完成程度。选项A如果不执行管理收尾就遣散资源,则项目的信息会丢失;选项C、D只是推迟了行动,并没有解决问题。