Initiating process group consists of the processes that facilitate the formal authorization to satart a new project or a project phase. Initiating processes are often done external to the project’s scope of control by the organization or by a program or portfolio processes which may blur the project boundaries for project inputs. Before beginning the initiation process group, ______.
A.a scope management plan is created to document how the project scope will be defined, verified and controlled
B.a project management plan is developed
C.specific activities that need to be performed to produce the various project deliverables are determined
D.none of the above
参考答案:D
解析: 启动过程组包含的过程用来正式授权启动一个新项目或项目阶段。启动过程组通常由项目所在组织通过项目集或项目组合管理来提供输入。在开始启动过程组之前应______。 A) 创建范围管理计划说明如何定义、验证和控制项目范围 B) 完成项目管理计划 C) 定义出一些特定活动用来产出不同的项目可交付成果 D) 以上选项都不对 选项A属于范围规划;选项B属于开发项目管理计划;选项C属于活动定义。都属于计划过程组,不会在启动阶段之前完成。