Your department is currently working on four urgent projects when it is assigned a major new project. To staff the new project, one of the four urgents needs to be terminated. The benefit cost ratios(BCR)for the four projects are listed. Which would you select for termination
A.0.8
B.1.1
C.0.9
D.1.9
参考答案:A
解析: 你的部门正在执行4个紧急的项目, 这时又分配了一个大型的新项目。为了给新的项目配备人员, 前4个项目必须中止一个。这4个项目的成本收益率(BCR)如下, 应该选择中止哪一个 A) 0.8 B) 1.1 C) 0.9 D) 1.9 项目的BCR越大越好。现在你需要终止一个项目, 当然终止最差的那个。