You are the project manager for a large government contract. The contract was signed a year ago for this three-year, multi-million dollar project. You were not involved in writing the contract or setting up change control procedures, but now you are being inundated with change requests from the project sponsor and from your own senior management. What should you do first

A.Ask senior management to set aside more management reserve to avoid potential financial problem

B.Tell the sponsor and your senior management that any changes are out of scope at his point and cannot be considere

C.Talk to your legal department to make sure you don’t do anything illega

D.Meet with the project sponsor and senior management to discuss this problem and potential solution

答案

参考答案:D

解析: 你是负责一个大型政府合同的项目经理。合同一年前签署, 将历时3年, 涉及数百万美元。你没有参与订立合同和建立变更控制过程, 但现在你面对着来自出资人和高级管理层多次的变更申请。首先你应该做什么 A) 请求高级管理层拨付更多的管理储备以避免潜在的财务问题。 B) 告诉出资人和高级管理层任何变更在此时都是超范围的, 不予考虑。 C) 与法律部门讨论确定你没有做任何违法的事。 D) 会见项目出资人和高级管理层来讨论这个问题和可能的解决方案。 目前的问题是缺乏变更控制过程,所以需要着手建立,选项D有助于解决此问题;选项A不解决根本问题;选项B不现实;选项C和题目无关。