Increasingly, the development of tourism is seen to have an effect on the environment. Erosion (磨损) is one problem. The steps and stones of major popular (51) like Shakespeare’s birthplace or Stonehenge (巨石阵) are literally being worn away by millions of foreign feet. The (52) in the case of Britain’s best known prehistoric monument has been to use railings to keep visitors at a distance. Such measures can hardly be (53) in the house of the Bard, however, where tourists want to enter the actual building.

Overcrowding in cities, towns and villages is (54) problem. Traffic jams are an outcome. In narrow roads, tourist vehicles cause congestion. (55) traders and residents cannot get around to do their work. Car parks fill up, (56) strangers park their cars where they can: in streets, across gateways, in lay-bys, or even in (57) driveways. This causes obstruction. The sheer weights of in-comers can be a hazard. Thus Venice, a city built for half a million inhabitants, is (58) by another half million who populate the city daily in the tourist (59) —eight million visits each year. The mayor recently decided to (60) visitors to 90,000 a day. the only way to save the city from overcrowding.

57().

A.public 

B.private 

C.remote 

D.personal

答案

参考答案:B

解析:

由句中的提示词even“甚至”可以推断,陌生人甚至把车停到了不该他们停车的车道上。四个选项中,A项public“公共的”和C项remote“遥远的”与题意不一致;D项personal意为“个人的”、“亲自的”,与private近义,但用在此处不合适;B项private指“私人的”,与public相对应,符合题意,是正确答案。

问答题

现计划建年产500万吨的化工厂,拟采用生产能力指数法估算主厂房设备投资。根据市场调查,已建成类似项目的生产98力和主厂房设备投资额分别为450万吨和1200万元;经测算,生产能力指数与综合调整系数分别为0.65和1.15。
经测算,与设备投资有关的其他各专业工程投资系数见表6-3,与主厂房投资有关的辅助工程及附属设施的投资系数见表6-4。
表6-3 与设备投资有关的其他各专业工程投资系数

投资项目名称 减压炉 真空系统 常压炉 自动化仪表 脱盐系统 换热系统 建安工程
投资系数 0.12 0.01 0.04 0.05 0.09 0.18 0.40
综合调整系数 1.05 1.05 1.05 1.10 1.10 1.10 1.25
            表6-4       与主厂房投资有关的辅助工程及附属设施的投资系数
投资项目名称 动力系统 机修系统 总图运输系统 行政生活福利设施工程 工程建设其他费用
投资系数 0.30 0.12 0.20 0.30 0.20
综合调整系数 1.05 1.10 1.10 1.10 1.25
本项目建设期3年,资金来源为自有资金。第1年投入30%,第2年投入50%,第3年投入20%;预计建设期物价平均上涨率3%,基本预备费率5%,投资方向调节税率为0。
【问题】1.用生产能力指数法估算主厂房设备投资。
2.用系数估算法估算该项目主厂房投资,并确定建筑安装工程费和设备购置费。
3.估算该项目的固定资产投资额,并编制固定资产投资估算表。
4.若固定资产投资流动资金率为5%,用扩大指标估算法估算项目的流动资金,确定项目的总投资。