问题 单项选择题

Each box is an activity; the number it contains is the duration of the activity in days.The duration of the critical path is ().

A.16days

B.14days

C.19days

D.20days

答案

参考答案:C

解析:

[分析]: 关键路径为最长时间的线路,3+6+7+1+2=19。