Each box is an activity; the number it contains is the duration of the activity in days.The duration of the critical path is ().
A.16days
B.14days
C.19days
D.20days
答案
参考答案:C
解析:
[分析]: 关键路径为最长时间的线路,3+6+7+1+2=19。