Extreme Programming (XP) is a discipline of software development with (71) of simplicity, communication, feedback and courage. Successful software development is a team effort-not just the development team, but the larger team consisting of customer, management and developers. XP is a simple process that brings these people together and helps them to succeed together. XP is aimed primarily at object-oriented projects using teams of a dozen or fewer programmers in one location. The principles of XP apply to any (72) project that needs to deliver quality software rapidly and flexibly.

An XP project needs a(an) (73) customer to provide guidance. Customers, programmers, managers, are all working (74) to build the system that’s needed.Customers-those who have software that needs to be developed-willleam simple, effective ways to (75) what they need, to be sure that they are getting what they need, and to steer the project to success.

(71)处填()。

A.importance

B.keys

C.roles

D.values

答案

参考答案:D

问答题

背景资料
某公路工程项目,路线长36.2km,双向4车道,路幅宽24.5m,设计车速80km/h,路面基层为水泥稳定土基层,根据工程实际情况及施工单位人力、设备条件,施工单位采用了路拌法水泥稳定土基层施工工艺。摊铺水泥日进度1.6km(单向),K6+200~K10+900路段具体施工过程如下:
(1)施工放样,恢复中线;根据施工布料需要在下承层上画布料网络。
(2)对水泥稳定土基层施工所需的土料、集料、水泥等按要求进行备料。
(3)确定松铺系数后,施工单位共用5d时间完成摊铺土任务。某日摊铺土2.5km。
(4)按规定洒水闷料,整平轻压。
(5)按规定摆放水泥,用刮板将水泥均匀摊开。
(6)为保证拌和质量,按规定采用了稳定土拌和机进行拌和。为了避免损坏下承层,拌和深度保持在下承层顶面5~10mm。
(7)拌和料拌和均匀后,立即用平地机初步整形,为保证整形质量,全路段平地机均由两侧路肩向路中心进行刮平。
(8)整形后,当混合料的含水率为最佳含水率(±1%~±2%)时,按规定用轻型压路机配合12t以上的压路机进行碾压。直线和平曲线段,由两侧路肩向路中心碾压,设超高的平曲线段,由外侧路肩向内侧路肩碾压。
由于部分工程量无法准确确定,业主和施工单位采用单价合同签订施工合同,业主委托甲监理公司进行施工监理,工程计量方式为监理工程师与施工单位联合计量。
问题:

写出该项目可采用的工程量计量方法,并指出路面工程计量应该采用的方法。