问题 阅读理解

阅读理解。

                                              Welcome to my shop

     This is my shop. It's near a school. There're many things in it. All students like to buy things here. Look!

  Here are ten pencils. They are pink and blue. They are on sale. You can buy a pencil for only 0.4 yuan.

 Do you like flowers? Here are five red flowers on the desk. One flower is one yuan. Do you see seven

 keys on the chair? They are black and look very nice. You can open the pencil-boxes with them. It is two

  yuan. The pencil-boxes are on the desk, too. Every pencil-box is five yuan. If you are hungry or thirty,

 you can also come to my shop and enjoy yourself.

1. You can open the _____ with the keys.

    A. doors          

    B. windows        

    C. pencil-boxes    

    D. desks

2. What colour are the pencils?

    A. Pink and blue.    

    B. Pink and red.    

    C. Red and black.  

    D. Blue and black.

3. The word "on sale" means (意思是) _____ in Chinese?

    A. 展示          

    B. 出售          

    C. 表演          

    D. 拍卖

4. Lily has ten yuan, and she can buy five pencils, one pencil-box, _____  key(s) and one flower.

    A. one            

    B. two            

    C. three          

    D. four

5. What can't you do in the shop?

    A. buy some stationery                

    B. eat or drink something

    C. buy some  flowers                

    D. play with balls

答案

1—5: CABAD

问答题

某建设项目,业主委托了监理单位,并与承包商签订了施工总承包合同。总承包合同约定的部分内容如下:

施工合同工期为240天,采用单价合同,土方工程综合单价为40元/m3,分项工程实际工程量超过工程量清单数量10%以上时调整单价,调整系数为0.85;人工单价为80元/工日,人工窝工费补偿标准为40元/工日;工作E、H使用同一台租赁设备,租赁费为1200元/天;工作F、I使用同一台自备设备,使用费为800元/天,其中折旧费为80元/天;工作K为专业性工程,允许分包。

承包商提交并经监理单位审批的施工进度计划如图4—1所示。

施工过程中发生了以下事件。

事件1:工作A为土方开挖工程,开挖中发现地质条件与勘察报告不相符。经补充勘察后调整了基础设计标高,使土方开挖量由60000m3增加至69000m3。采取赶工措施后原计划工作持续时间未受影响。

事件2:工作E完成后,由于业主进行设计变更,致使工作H延期25天开工、工作I延期15天开工,两项工作均按计划工作持续时间完成,总计入员窝工86工日。其他工作未受影响。承包商向业主提出工期索赔和费用索赔。

事件3:工作K分包时,分包商向业主提交资质审查资料。为保证施工质量,承包商根据以往经验,将工作K原设计尺寸扩大,分包商按承包商要求实施后,向业主申报了增加的工程量并提出相应费用补偿要求。

问题

针对事件2,总承包商是否可向业主提出工期索赔要求说明理由。列式计‘算总承包商可向业主提出的费用索赔额。