You are running a project for a customer based on a cost reimbursable contract with the following terms:Target costs,$1000000;fix fee,100000;benefit/cost sharing,80/20;price ceiling,1200000.Which is the PTA (point of total assumption,break point)of the project ?()
A.$1300000.
B.$1500000.
C.$80000.
D.$1125000.