In your construction project, the CPI is 1.30 and SPI is 0.85. What could be the potential reason
A) A critical resource went on sick leave for a long period of time, which had not been anticipated earlier.
B) The Cost of raw materials required for construction increased 10%.
C) You had not taken into account inflation rate.
D) There was 4 days waiting time in the curing of cement, and work could not be done during that time.
参考答案:A
解析: 你所在的建筑项目的CPI为1.3, SPI为0.85。下列哪项是潜在的原因
A) 关键资源长时间离开, 这是之前没有预料到的。
B) 建筑所需材料的成本增加了10%。
C) 你以前没考虑通货膨胀率。
D) 在水泥加工中有四天的等待时间, 这段时间内无法工作。
选项B、选项C都会增加成本,但是这个项目成本没有问题(CPI>1),我们可以忽略这两个选项。选项D是个已知的因素,在项目进度计划中已经考虑。只有选项A最可能导致进度落后。