You are a project manager of a small construction project. Your project was budgeted for US $72,000 over a six week period. As of today, you’ve spent US $22,000 of your budget to complete work that you originality espected would cost US $24,000. According to your schedule, you should have spent US $30,000 by this point. Based on these circumstances, you project could be BEST described as ______ .
A) under budget
B) over budget
C) on budget
D) need more info
参考答案:A
解析: 你是一个小型建筑项目的项目经理。你的项目预算是72000美元, 历时6周。至今你已经支出了22000美元用于完成你预期花费24000美元的工作。根据你的进度计划, 你在这个时问点应该已经支出了30000美元。这种情况下, 你的项目可以描述为 ______ 。
A) 低于预算 B) 超出预算
C) 按照预算执行 D) 没有足够的信息
本题BAC=72000;PV=30000;AC=22000;EV=24000。CV=EV-AC=2000。CV大于零表示低于预算。