问题 完形填空

改写后的课文内容填空(共10个空,每空1分,满分10分)(给出首字母)

Li Daiyu and her cousin Liu Qian were on a trip to Canada to visit their cousins. They decided to catch the train, The True North, to cross the whole c______.

They began their journey in Vancouver, a city s______ by mountains and the Pacific Ocean. A______ the train, the cousins settled down in their seats. When they crossed the Rocky Mountains, they managed to catch s______ of some mountain goats and even a grizzly bear and an eagle. In Calgary, they learned that cowboys, most of whom had a g______ for riding horses, came from all over the world to compete there in the Stampede.

After two days’ travel, the girls began to realize that Canada is quite e______. At school, they had learned that most Canadians live within a few hundred kilometers of the USA b______, and that Canada’s population is only s______ over thirty million, but still they were a______ to see such a large country with so small a population.

That night as they slept, the train rushed southward towards Toronto, the biggest and most w______ city in Canada.

答案

71.continent           72. surrounded              73. Aboard            74. sight         75. gift

76. empty                     77. boarder            78. slightly            79. amazed     80. wealthy

多项选择题

场景(一)


某广播电视中心工程,发包人与承包人根据《建设工程施工合同(示范文本)》(GF-99-0201)签订了施工承包合同。因急于开工且地质条件复杂,基础工程(含土方开挖)部分采用成本加酬金计价方式,其他部分采用单价合同计价方式。承包人与钢结构分包人根据《建设工程施工专业分包合同(示范文本)》(GF-2003-0213)签订了屋面钢结构安装专业分包合同。在工程实施过程中,发生了如下暂停施工事件:
事件1:在土方开挖时,基坑东南角实际的地质条件与勘察报告严重不符,需停工复勘,并进行设计修改。
事件2:施工现场临时用电敷设情况与承包人报送的临时用电专项方案不符,需停工整改。
事件3:运送渣土严重污染了临近城市道路,影响了市容,被城管部门查处,需停工整改。
事件4:发包人提供的预制管桩桩头有质量问题需处理。
事件5:发包人为了确保项目能按期启用,要求承包人调整已经被确认的施工方案。发生了上述事件后,承包人及时向监理工程师提交了索赔意向通知,要求发包人给予补偿。

根据《建设工程合同示范文本》,以下内容表述正确的有( )。

A.发出开通通知应该由发包人委托监理人执行

B.监理应组织设计单位向承包人进行设计交底

C.监理人未及时发出复工指示,责任由发包人承担

D.监理人应在开工7个工作目前向承包人发出开工通知

E.由发包人原因引起暂停施工的,承包人有权要求赔偿工期延误,增加费用和利润