某工程计划进度与实际进度如下表所示。表中实线表示计划进度(计划进度线上方的数据为每周计划投资),虚线表示实际进度(实际进度线上方的数据为每周实际投资)。各分项工程每周计划完成和实际完成的工程量相等。
问题:计算投资数据,并将结果填入下表。
投资数据表 单位:万元
项目 | 投资数据 | |||||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | |
每周拟完工程计划投资 | ||||||||||||
拟完工程计划投资累计 | ||||||||||||
每周已完工程实际投资 | ||||||||||||
已完工程实际投资累计 | ||||||||||||
每周已完工程计划投资 | ||||||||||||
已完工程计划投资累计 |