The owner (buyer) of a project usually has the right to direct changes to the scope of work while the project work is being accomplished. Often, the owner will orally request a change and insist that the change be initiated immediately without the normal documentation (e.g.a change order). When the change be initiated without documentation ______.
A) the owner assumes all responsibility for paying for the change although the owner may at a later not want the change
B) the owner assumes responsibility for one-half the cost of the change until the documentation is completed and all at the same time
C) the project manager assumes all risk for the change, if initiated, until the documentation is received
D) the project manager assumes only the risk of misinterpreting the owner's oral change directive, while the owner assumes responsibility for paying for the request change
参考答案:C
解析:因此一定要有相应文档。
项目的所有者通常有权力修改项目的范围。经常,项目所有者口头上提出变更并坚持不需要正常文档(例如变更通知单)。当不需文档起动变更时______。
A) 所有者在变更时需要承担全部责任
B) 所有者应该承担变更成本的一半直至完成文档
C) 项目经理承担所有变更风险直至收到相应的文档
D) 项目经理只承担误解口头变更的行为,而所有者承担要求变更的责任