问题 单项选择题

关于与房屋征收相关的工作,描述错误的是()。

A.调查结果应在房屋征收范围内进行保密

B.暂停办理相关手续的书面通知应当载明暂停期限,暂停期限最长不得超过1年

C.市、县级人民政府及有关部门对认定为超过批准期限的临时建筑,不予补偿

D.做出房屋征收决定前,征收补偿费用应当足额到位、专户存储、专款专用

答案

参考答案:A

阅读理解

阅读理解。

     The polar bear is a very big white bear. We call it the polar bear because it lives inside the Arctic near

the North Pole. There are no polar bears at the South Pole.

     The polar bear lives in the snow and ice. At the North Pole there is only snow and water. There is not any

land. You can not see the polar bear in the snow because its coat is yellow white. It has a very warm coat

because the weather is cold at the north of the Arctic.

     The bear is three meters long, and it weighs 450 kilos. It can stand up on its back legs because it has very

wide feet. It can use its front legs like arms. The polar bear can swim very well. It can swim 120 kilometers

out into the water. It catches the fish and the sea animals for food. It goes into the sea when it is afraid.

     People like to kill the polar bear for its beautiful white coat. The governments of Canada, the USA and

Russia say that no one can kill polar bears now. They do not want all of these beautiful animals to die.

1. The polar bear lives _____.

A. at the South Pole

B. near the North Pole

C. in warm countries

D. on land

2. At the North Pole there is no _____.

A. ice

B. snow

C. water

D. land

3. You can not see the polar bear in the snow because _____.

A. it has a yellow white coat

B. it can run very fast

C. it goes under the snow

D. it goes into the water

4. The polar bear _____ for food.

A. catches land animals

B. catches sea animals and fish

C. looks for trees

D. looks for fruit and vegetables

5. When the polar bear is afraid, it _____.

A. goes into the sea

B. runs away

C. goes under the snow

D. stands up on its wide feet

问答题 案例分析题

施工进度控制方法的应用案例分析题:

某工程,施工合同中约定,工期19周;钢筋混凝土基础工程量增加超出15%时,结算时对超出部分按原价的90%调整单价。经总监理工程批准的施工总进度计划如图2—8所示,其中A、C工作为钢筋混凝土基础工程,B、G工作为片石混凝土基础工程,D、E、F、H、J工作为设备安装工程,K、L、J、N工作为设备调试工作。

施工过程中,发生如下事件。

事件1:合同约定A、C工作的综合单价为700元/m3。在A、C工作开始前,设计单位修改了设备基础尺寸,A工作的工程量由原来的4200m3增加到7000m3,C工作工程量由原来的3600m3减到2400m3。

事件2:A、D工作完成后,建设单位拟将后续工程的总工期缩短2周,要求项目监理机构帮助拟定一个合理的赶工方案,以便与施工单位洽商,项目监理机构提出的后续工作可以缩短的时间及其赶工费率见表2—4。

【问题】

1.事件1中,设计修改后,在单位时间完成工程量不变的前提下,A、C工作的持续时间分别为多少周?对合同总工期是否有影响?为什么?A、C工作的费用共增加了多少?

2.事件2中,项目监理机构如何调整计划才能既实现建设单位的要求又能使赶工费用最少?说明理由。增加的最少赶工费用是多少?

3.对表2-5中未通过的调试工作,根据施工合同进行责任界定,并确定应补偿施工单位的费用。