What is true when a change control system's provision for changes without formal review in case of emergency is being utilized
A) Changes can be simply applied without further managerial activities if they help solving the problem.
B) Changes must still be documented and captured so that they do not cause problems later in the project.
C) A new change control board should be established.
D) The project baseline must be changed as well.