A project manager believes that modifying the scope of the project may provide added value service for the customer.The project manager should______.
A.assign change tasks to project members
B.call a meeting of the configuration control board
C.change the scope baseline
D.postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
参考答案:D
解析:项目经理认为调整项目范围可以给客户提供增值的服务,项曰经理应该怎么做。 选项A是安排任务变更到项目成员,选项B是召集变更控制委员会会议,选项C是变更项目基线,选项D是按照原先的基线,在确定完成一项改进项目会得到客户的相应资金前,暂缓修改。 由于是在原内 * * 础上增加增值服务内容,超出原先范围,应先确定客户认可和增加新资金,因此应选择D。