作为施工单位,采用( )合同形式,可最大限度减少风险。
A.不可调值总价
B.可调值总价
C.单价
D.成本加酬金
参考答案:D
下列地点中符合“北半球,东半球”的点是( )
A.(35°N,150°E)
B.(25°N,40°W)
C.(70°N,170°E)
D.(25°S,15°E)
In managing a project,you notice that a deliverable mentioned in the general conditions of the contract has not yet been received.The seller,however,says the special provisions of the contract void that deliverable.What should you do ?()
A.Require the deliverable as in the contrac
B.Do nothin
C.Contact the contract manage
D.Send a letter requiring the deliverable is me