问题 改错题

短文改错。文中共有10处错误,每句中最多有两处。错误涉及一个单词的增加、删除或修改。

增加: 在缺词处加上一个漏词符号(∧),并在此符号下面写出该加的词。

删除: 把多余的词用斜线(\)划掉。

修改: 在错的词下划一横线,并在该词下面写出修改后的词。

注意: 1. 每处错误及修改均仅限一词;

            2. 只允许修改10处,多者(从第11处起)不计分。

    Our school lies on the foot of a mountain with a small river passes by. It used to be a quiet, clean and

beautiful place for a school. It is a pity which things have changed after a chemical factory was built near

our school one year ago. Every day the factory produces many waste water and some harmful gases. The

terribly pollution is harmful to our health. What's bad, the great noise from the factory had a bad effect on

our activities. As a result, our school is no longer what it used to. Our teachers and students are miserable

beyond the description.

_______________________________________________________________________________________

答案

第一句:1. on→at  2. passes→passing 

第三句:3. which→that  4. after→since  

第四句:5. many→much

第五句:6. terribly→terrible 

第六句:7. bad →worse  8. had→has 

第七句:9. used to后加be 

第八句:10. 去掉the

单项选择题 A1/A2型题
问答题

某实施施工监理的工程,建设单位按照《建设工程施工合同(示范文本)》为甲施工单位签订了施工总承包合同。合同约定开工日期为2006年3月1日,工期为302天,建设单位负责施工现场外道路开通及设备采购;设备安装工程可以分包;甲施工单位通过筛选与乙施工单位签订了安装分包合同。经总监理工程师批准的施工总进度计划如图6-3所示。

在施工过程中发生了如下事件。

事件1:由于道路没有及时开通,使开工日期推迟到2006年3月4日,并造成施工方经济损失3万元,为此,施工单位于2006年3月10日向监理单位提出延长工期的索赔。

事件2:在基础工程施工中,由于遭遇特大暴雨,土方工程发生滑坡,造成人员、机械损失共计5万元,导致C工作持续时间延长12天,为此提出经济补偿与工期的延期。

事件3:在主体施工过程中,甲施工单位为保证工程质量,改进了混凝土泵浇注的施工工艺,延误F工作时间10天,为此甲施工单位向建设单位提出延期10天的申请。

事件4:设备安装工程完工后进行验收,第一次试车验收结果不合格,经检查分析,是由于设备本身质量有问题造成的,为此乙施工单位提出将已安装的设备拆除,重新安装,并重新组织试车验收。为此造成J工作持续时间延长24天,费用增加6万元,甲施工单位就此提出工期和费用索赔。

1.事件1中,监理单位应如何答复说明理由。

2.事件2中,监理单位应采取什么措施并对施工单位提出哪些要求就施工单位提出的索赔,监理单位应如何答复说明原因。

3.事件3中,甲施工单位改进施工工艺应遵循什么审批程序对甲施工单位的延期申请,监理单位应如何答复说明理由。

4.事件4中的验收应由谁来组织监理单位对甲施工单位的索赔要求如何处理说明理由。乙施工单位可得到的补偿是什么说明原因。