问题
单项选择题
施工进度检查的主要方法是将经过整理的实际进度数据与计划进度数据进行比较,其目的是( )。
A.分析影响施工进度的原因
B.掌握各项工作时差的利用情况
C.提供计划调整和优化的依据
D.发现进度偏差及其大小
答案
参考答案:D
施工进度检查的主要方法是将经过整理的实际进度数据与计划进度数据进行比较,其目的是( )。
A.分析影响施工进度的原因
B.掌握各项工作时差的利用情况
C.提供计划调整和优化的依据
D.发现进度偏差及其大小
参考答案:D
完形填空。 | |||
Mark has a big garden, and it is very nice. There 1________ some tall trees and beautiful flowers in the garden. Many birds like 2________ in it. They often sing and dance there. Beside the trees and flowers, there is a small lake. Mark usually 3________ games with his friends in the garden. His parents likes fishing 4________ the lake. What about Mark's cat? 5________ sometimes sleeps in the trees, sometimes plays with a ball under the trees.
|