问题
单项选择题
某分部工程有两个施工过程,分为4 个施工段组织流水施工,流水节拍分别为3、4、4、5 天和4、3、4、5 天,则流水步距为( )天。
A.3
B.4
C.5
D.6
答案
参考答案:C
某分部工程有两个施工过程,分为4 个施工段组织流水施工,流水节拍分别为3、4、4、5 天和4、3、4、5 天,则流水步距为( )天。
A.3
B.4
C.5
D.6
参考答案:C
Dear Nancy I am happy to tell you my school and my life. Every day my father drives me to school. My school is very big and beautiful. I like my school very much. The desks and chairs are new. There are lots of pictures on the walls. You can also see some flowers on the teachers’ desk. We clean the classroom every day. I don’t go to school on Saturday and Sunday. I get up at six on Saturday. I play basketball with my father in the park near my home for half an hour. Then I eat my breakfast. I help my mother water the trees and flowers in the garden. At eight I begin to do my homework. My parents and I have lunch in the KFC. In the afternoon. I have Art lessons. Sometimes I play computer games or chat with my friends on the Internet in the evening. I like my weekend very much. Yours Li Hua
|