问题 单项选择题

关于施工总承包管理模式的说法,错误的是()。

A.在进行对施工总承包管理单位的招标时,只确定施工总承包管理费,而不确定工程总造价,这可能成为业主控制总投资的风险

B.-部分施工图完成后,业主就可单独或与施工总承包管理单位共同进行该部分工程的招标,分包合同的投标报价和合同价以施工图为依据

C.业主只需要进行一次招标.与施工总承包商签约,因此招标及合同管理工作量将会减小

D.不需要等待于施工图设计完成后再进行施工总承包管理的招标,分包合同的招标也可以提前,这样就有利于提前开工,有利于缩短建设周期

答案

参考答案:C

解析:选项C是施工总承包模式的特点。一般情况下,在施工总承包管理模式下,所有分包合同的招标投标、合同谈判以及签约工作均由业主负责,业主方的招标及合同管理工作量较大。

阅读理解

On an island there are exactly seven towns: T, U, V, W, X, Y and Z. All existing and planned roads on the island are two-way and run perfectly straight between one town and the next. All distances(距离;路程) by road are distances the main square of one town to the main square of another town. U is the same distance by road from T, V and W as Y is from X and Z. The following are of the now existing roads on the islands.

Road 1 goes from T to V via (经由) U.

Road 2 goes directly from U to W.

The triangle (三角形) road goes from X to Y, from Y on to Z, and from Z back to X. Any main square reached by two roads is an interchange (立交桥) between them, and there are no other interchanges between roads.

68. Which of the following sketches is correct?

A.     W                     B.        U

                                        

T   U    V                       W   V   T

C.   T   U    V    W         D.       T    W    V

U

69. Draw a sketch of the Triangle Road. Which of the following sketches is correct?

A.        Z                     B.     Y      X

     Y                                 

Z

X                          

C.   X     Z                      D.    Y     Z   

        

Y                                   X

70. Which of the following is a town from exactly two other towns can be reached by road?

A. T           B. X          C. V         D. W

填空题