问题
单项选择题
在进行建设工程项目总进度目标控制前,首先应( )。
A.制定项目进度控制的措施
B.对项目实施进行总体部署
C.分析和论证进度目标实现的可能性
D.编制施工总进度规划
答案
参考答案:C
在进行建设工程项目总进度目标控制前,首先应( )。
A.制定项目进度控制的措施
B.对项目实施进行总体部署
C.分析和论证进度目标实现的可能性
D.编制施工总进度规划
参考答案:C
完形填空。 | ||||
A sad little boy was in search of happiness and wanted to meet God (上帝). On his way, he saw an elderly woman 1 in a park watching some birds. The boy sat down 2 her. He opened his bag to-take a drink, when he noticed the lady looked 3 . So he offered her a piece of cake. She accepted it and smiled at him. Her 4 was so wonderful that he wanted to see it again. Then he offered her a can of coke. Once again she smiled at him. The boy was pleased! They 5 there all afternoon, eating and smiling without saying a word. 6 it began to grow dark, the boy got up to leave, but before he had gone no more than a few steps, he turned around, ran 7 to the old woman and gave her a big hug (拥抱). She gave him her biggest smile ever. When the boy arrived home, his mother was 8 by the look of joy on his face. She asked, "What has made you so happy today?" He 9 , "I had lunch with God. She's got the most beautiful smile in the world!" And when the old woman returned to her home, she told her son that she had lunch with God. Too often we overlook (忽视) the 10 of a touch, a smile, a kind word, a listening ear, or the smallest act of caring. However, all of these have the possible power to turn a life around. | ||||
|