单项选择题
某建筑工程投入使用后,建设单位发现车库挡土墙发生偏移,经分析测算原因是设计挡土墙截面过小所致,建设单位委托施工单位进行了修缮加固处理,该部分费用施工单位应向()索赔。
A.设计单位
B.建设单位
C.审图单位
D.监理单位
答案
参考答案:B
某建筑工程投入使用后,建设单位发现车库挡土墙发生偏移,经分析测算原因是设计挡土墙截面过小所致,建设单位委托施工单位进行了修缮加固处理,该部分费用施工单位应向()索赔。
A.设计单位
B.建设单位
C.审图单位
D.监理单位
参考答案:B
Macklin Metals has received 80 million pounds sterling. The company plans to spend $120 million on a project in the United States in 90 days. Macklin inters into a cash settlement currency forward to exchange the pounds for U. S. dollars at a rate of $1.50 per pound in 90 days. If the exchange rate is $1.61 per pound at the settlement date, the cash settlement Macklin will pay or receive is closest to: