问题
单项选择题
FIDIC合同通用条件规定,业主收到监理工程师提交的中期付款证书( )内或最终支付证书的( )内应向承包人付款,否则将要支付延期付款利息
A.20天;45天
B.45天;56天
C.28天;56天
D.20天;45天
答案
参考答案:C
FIDIC合同通用条件规定,业主收到监理工程师提交的中期付款证书( )内或最终支付证书的( )内应向承包人付款,否则将要支付延期付款利息
A.20天;45天
B.45天;56天
C.28天;56天
D.20天;45天
参考答案:C
A firm ended the last period with inventory of $ 4.0 million and a last in, first out (LIFO) reserve of $175000. During the year, it made purchases of $ 2. 0 million and reported sales of $ 5.5 million with a gross margin of 0.32. At the end of the year, it reported a LIFO reserve of $ 75000. What is the value of the firm’ s cost of goods sold (COGS) on a first in, first out (FIFO) basis
A.
A. $ 384000O. |
B.
B. $ 3740000. |
C.
C. $ 3640000. |