You got news that because of bad weather, your shipment has got delayed by 2 weeks。What should be the first step that you take
A.Fast track the project to ensure that the project schedule is not delaye
B.Review the performance reports to determine which planned dates have not been met, and the impact on critical pat
C.Try to get additional supplies from an alternate location as soon as possibl
D.Take corrective action to minimize the impact because of the dela
参考答案:B
解析: 你得到一个消息, 由于天气不好, 你的货船推迟了2周。这时, 你首先应采取什么行动 A) 快速跟进此项目, 确保项目进度不会被耽误。 B) 回顾绩效报告, 判断哪些计划的日期没有被满足, 以及对关键路径的影响。 C) 尽快从其他可替代的地方获得额外的补给。 D) 采取纠正措施最小化由于延迟带来的影响。 问的是第一步,首先需要看绩效报告,报告里面有进度绩效信 息,可以看出是否对关键路径有影响。