In your project, you are in the process of creating an activity list. This should contain all the following EXCEPT ______ .
A.activities that are not required as part of project scope
B.activities that are to be performed as part of the project
C.activity identifier and scope of work description for each schedule activity
D.all the above are included in the activity list
答案
参考答案:A
解析: 你正在创建项目的活动列表。活动列表必须包括下列所有项, 除了 ______ 。 A) 不是项目范围所要求的部分的活动 B) 作为项目一部分需要被执行的活动 C) 用于每个进度活动的活动标识和工作范围描述 D) 上面所有几项都包括在活动列表内 活动列表不包括不属于项目范围的进度活动。