The project time management processes include ______ .
A.define activities, sequence activities, estimate activity resources, and estimate activity durations
B.define activities, activity sequencing, and activity duration estimating
C.activity identification, activity execution, and activity results
D.activity determination, activity duration estimating, activity implementation, and activity results
参考答案:A
解析: 项目时间管理过程包括 ______ 。 A) 活动定义、活动排列、估算活动资源、估算活动历时 B) 活动定义、活动排序、活动历时估算 C) 活动识别、活动执行、活动结果 D) 活动确定、活动历时估算、活动实施、活动结果 项目进度管理包括的过程有:活动定义、活动排序、活动资源估算、活动历时估算、进度编制、进度控制等。