Which of the following documents is not used as input for product acceptance
A) The project scope statement, it describes the acceptance criteria.
B) The project scope management plan, it describes the acceptance process.
C) The work breakdown structure(WBS), it describes the deliverables for acceptance.
D) The RACI matrix, it describes accountabilities in case of product rejection.