问题 单项选择题

The Estimate Activity Resource process is closely coordinated with the (73)process.

A.Estimate Costs

B.Sequence Activities

C.Plan Communications

D.Conduct Procurements

答案

参考答案:A

解析:参考译文估算活动资源与成本估算是密切联系的。