问题 单项选择题

Project work packages are typically decomposed into smaller components called activities to provide a basis for (72), scheduling, executing, and monitoring and controlling the project work.

A.reviewing

B.estimating

C.auditing

D.expecting

答案

参考答案:B

解析:参考译文把项目工作包分解成更小的称为活动的单元,为估算、进度安排、项目执行、项目监控提供了基础。