A management control point can be placed at selected management points (specific components at selected levels)of the WBS above. the work package level. These control points can be ______ .
A.used for rolling wave planning
B.decomposed further to help in creation of work authorization system
C.used for planning known work content that does not have detailed schedule activities
D.used as a basis for planning when associated work packages have not yet been planned