You are the project manager for a large government contract. The contract was signed a year ago for this three-year, multi-million dollar project. You were not involved in writing the contract or setting up change control procedures, but now you are being inundated with change requests from the project sponsor and from your own senior management. What should you do first
A.Ask senior management to set aside more management reserve to avoid potential financial problem
B.Tell the sponsor and your senior management that any changes are out of scope at his point and cannot be considere
C.Talk to your legal department to make sure you don’t do anything illega
D.Meet with the project sponsor and senior management to discuss this problem and potential solution